Reconstruction of  the tram substation in Alexandria / Egypt

Basic informations:

Refurbishment of the original CKD technology supplied in 70s of the last century which was out of service. The main task of the project was to manage connecting between supplied modern technology and the existing facilities within the re-commissioning of the tram substation Moustafa Kamel in Alexandria

Scope of delivery:

Delivery with installation and commissioning of DC cabinets comprising 14 fields, including input field of 4 pc rectifiers, output and standby feeders in withdrawable design and cabinet of lengthways connector, all of CKD ELEKTROTECHNIKA production.  Transfor-mers, medium voltage switchgear 10.5kV, rectifiers and assembly of equipment for self- consumption are preserved from the original technology customer.

  • Project
  • Complete documentation
  • Set of spare parts
  • Installation and commissioning
  • Staff training.

 

Development of the project:

Signing of the contract 12/2013
Commissioning 01/2015