COGEN II – boiler house Stara Lipa


Scope of works:
 

delivery and installation of 3 pieces of cogeneration units based on MWM gensets

 

Technical parameters: 

  • 2pc of TCG2020 V20 + 1 pc of TCG2020 V12
  • total electrical output: 5050 kWe
  • total heat capacity: 5380 kWt

Completion date: 2010-2011
Commissioning: 02-05 / 2011