3x133.3 MW Cankiri Orta coal-fired power plant - Turkey (YOTES Project)

Project parameters:

  • preparation and delivery of engineering for 3x133.3 MW coal-fired power plant

Project management:

  • EPC-M based project management 
  • provision of BOP components of the power plant
  • I&C delivery
  • delivery of other operating systems
  • subcontracts from other Czech and EU manufacturers

Location: Cankiri Orta, Turkey
Commissioning: commissioning of first power plant´s production unit in 2014